Accept Bid of $ $34,981.00 from Manzanita Landscaping to construct an Outdoor Learning Center at the Launch Pad Teen Center as part of the PY18 CDBG Program.

Information

Department:Community DevelopmentSponsors:
Category:Approval

Attachments

  1. Printout
  2. Manzania Landscaping Proposal (This file has not yet been converted to a viewable format)
  3. Landscape Design

Document Comments

Recommended Action: MOVE to award the bid to Manzanita Landscaping for $34,981.00 and authorize the City of Prescott to execute the contract with The Launch Pad Teen Center to complete the Outdoor Learning Center Project.

 

Body

Item Summary

 

The Launch Pad Teen Center was awarded a PY18 CDBG Grant in the amount of $35,000.00. This award was recommended by the CDBG Citizen Advisory Committee (CAC) and approved by the Prescott City Council. The Launch Pad received three bids for the outdoor learning center.

 

The Launch Pad Teen Center has chosen to go with the second lowest bid of Manzanita Landscaping because the lowest bid was incomplete and did not include all critical components of the bid request. Manzanita’s bid did have all components and also included a rainwater harvesting system to fuel a new irrigation system and native plantings.

 

Background

 

This project is part of the City of Prescott’s CDBG Annual Action Plan of 2018.  The project was competitively applied for and reviewed by the seven (7) member City of Prescott CDBG Citizen’s Advisory Committee (CAC) and approved by the Prescott City Council and by the US Department of Housing and Urban Development (HUD).

 

City staff completed the HUD required environmental assessment and reviewed the project and bidding process. Per the contract, all work must be substantially complete within 45 calendar days of the notice to proceed.  The existing contract will be amended to include new timelines for the project.

 

Financial Impact

 

This program is funded on a cost reimbursement basis to the sub-recipients/grantees and Prescott will be reimbursed from HUD as payments are made to sub-recipients.

 

 

Meeting History

Jul 9, 2019 3:02 PM  City Council Voting Meeting
draft Draft
RESULT:APPROVED [UNANIMOUS]
MOVER:Steve Sischka, Councilman
SECONDER:Billie Orr, Mayor Pro Tem
AYES:Greg Mengarelli, Billie Orr, Steve Blair, Phil Goode, Jim Lamerson, Alexa Scholl, Steve Sischka